Lake Saint Louis Boulevard; coming along
April 25, 2009
Lake Saint Louis, MO
At Monday’s Board of Aldermen meeting, Derek Koestel, Director of Public Works, explained the timeline of the Lake Saint Louis Boulevard construction project.
Koestel stated that in about two and a half weeks, the paving should be done all the way up to the Spillway Bridge. Then, Koestel said, “another month or so to get the guard rail and the rest of the work there done.”
By mid-July, Lake Saint Louis should have brand new pavement almost all the way from Highway N through to the Spillway Bridge, he indicated.